itexamable.com

CISA Exam-Test 16

/30
224

CISA EXAM-TEST 16

1 / 30

1. Which of the following BEST measures project progress?

2 / 30

2. An IS auditor has been asked to review the implementation of a customer relationship management (CRM) system for a large organization. The IS auditor discovered the project incurred significant over-budget expenses and scope creep caused the project to miss key dates. Which of the following should the IS auditor recommend for future projects?

3 / 30

3. Which of the following is protocol data unit (PDU) of transport layer in TCP/IP model?

4 / 30

4. While evaluating the "out of scope" section specified in a project plan, an IS auditor should ascertain whether the section:

5 / 30

5. An IS department is evaluated monthly on its cost-revenue ratio user satisfaction rate, and
computer downtime This is BEST zed as an application of.

6 / 30

6. An IS auditor is involved in the reengineering process that aims to optimize IT infrastructure. Which of the following will BEST identify the issues to be resolved?

7 / 30

7. Which of the following is protocol data unit (PDU) of network interface layer in TCP/IP model?

8 / 30

8. Which of the following is the MOST effective way to reduce risk to an organization from widespread use of web-based communication technologies?

9 / 30

9. At the completion of a system development project, a post-project review should include which of the following?

10 / 30

10. Which of the following has the MOST significant impact on the success of an application systems implementation?

11 / 30

11. Which of the following types of risk could result from inadequate software baselining?

12 / 30

12. An organization is implementing an enterprise resource planning (ERP) application. Of the following, who is PRIMARILY responsible for overseeing the project to ensure that it is progressing in accordance with the project plan and that it will deliver the expected results?

13 / 30

13. An IS auditor is assigned to audit a software development project, which is more than 80 percent complete, but has already overrun time by 10 percent and costs by 25 percent. Which of the following actions should the IS auditor take?

14 / 30

14. A company's development team does not follow generally accepted system development life cycle (SDLC) practices. Which of the following is MOST likely to cause problems for software development projects?

15 / 30

15. When reviewing an active project, an IS auditor observed that the business case was no longer valid because of a reduction in anticipated benefits and increased costs. The IS auditor should recommend that the:

16 / 30

16. Which of the following transmission media is MOST difficult to tap?

17 / 30

17. Which of the following is MOST relevant to an IS auditor evaluating how the project manager has monitored the progress of the project?

18 / 30

18. While reviewing an ongoing project, the IS auditor notes that the development team has spent eight hours of activity on the first day against a budget of 24 hours (over three days). The projected time to complete the remainder of the activity is 20 hours. The IS auditor should report that the project:

19 / 30

19. Which of the following INCORRECTLY describes the layer function of the Application Layer within the TCP/IP model?

20 / 30

20. An IS auditor is assessing the results of an organization's post-implementation review of a
newly developed information system. Which of the following should be the auditor's MAIN focus?

21 / 30

21. An IS auditor has been asked to participate in project initiation meetings for a critical project. The IS auditor's MAIN concern should be that the:

22 / 30

22. Which of the following types of risk is MOST likely encountered in a software as a service (SaaS) environment?

23 / 30

23. Which of the following should an IS auditor review to understand project progress in terms of time, budget and deliverables for early detection of possible overruns and for projecting estimates at completion (EACs)?

24 / 30

24. A rapid application development (RAD) methodology has been selected to implement a new enterprise resource planning (ERP) system. All of the project activities have been assigned to the contracted consulting company because internal employees are not available. What is the IS auditor's FIRST step to compensate for the lack of resources?

25 / 30

25. While evaluating software development practices in an organization, an IS auditor notes that the quality assurance (QA) function reports to project management. The MOST important concern for an IS auditor is the:

26 / 30

26. An organization is running servers with critical business application that are in an area subject
to frequent but brief power outages. Knowledge of which of the following would allow the
organization's management to monitor the ongoing adequacy of the uninterruptable power supply
(UPS)?

27 / 30

27. An IS auditor finds that a system under development has 12 linked modules and each item of data can carry up to 10 definable attribute fields. The system handles several million transactions a year. Which of these techniques could an IS auditor use to estimate the size of the development effort?

28 / 30

28. Which of the following transmission media is LEAST vulnerable to cross talk?

29 / 30

29. Which of the following should be an IS auditor's PRIMARY concern after discovering that the scope of an IS project has changed and an impact study has not been performed?

30 / 30

30. An IS auditor performing a review of a major software development project finds that it is on schedule and under budget even though the software developers have worked considerable amounts of unplanned overtime. The IS auditor should:

Eco Bags in Dubai | Eco Bags in UAE | Eco Bags in Sharjah